Despite the significant area involved, the installation process proved straightforward. The contractor described the product as being similar to assembling a jigsaw puzzle, allowing installation teams to quickly become familiar with the system.
Laying the completed sections was described as simple and efficient. Installation teams built larger sections before placing them, helping maximise productivity across the site.
The contractor highlighted the speed of installation as one of the key benefits of the system, reporting that crews were able to install approximately 1,200m² in a single day.
This level of productivity helped maintain progress across a project covering a substantial 21,000m² area.