Home
My Geoworks
Severn Trent Earl Shilton Treatment Works

Earl Shilton Treatment Works

  • Severn Trent

  • Earl Shilton Sewage Treatment Works

  • E'GRID

We were approached by Severn Trent’s contractor to discuss the creation of site access and a proposed working platform to be installed at the sewage treatment works at Earl Shilton, southwest of Leicester.

The works were being developed to increase its waste processing capacity. The proposed plant for the site works required temporary works access as well as a working platform for the concrete pump and hydraulic (Kobelco CKE700) crawler crane.

The traditional approach to working platform design is to use a BR470 design methodology as suggested by BRE – Working Platforms for Tracked Plant (2004). Instead, our technical team proposed using a form of load spread analysis incorporating the use of E’GRID Biaxial geogrid. This meant the working platform thickness could be reduced by a further 40% compared to BR470.

Although the application area was not large, when operating in such confined spaces, the benefit was significant. Reducing the resources required can have a very positive impact on such a restricted site, not only reducing costs but also minimising the contractor’s construction programme and overheads.

Earl Shilton

The value-engineered solution provided by Geoworks cut our costs by 40%. We were very pleased with the savings made, but also the technical support and the professional levels of service provided.

Sam Harris

MWH Global (Stantec)

Earl Shilton

Within a well-managed time frame, the technical team was able to value engineer the traditional approach to working platform construction. With tight site constraints and limited resources, the impact on value engineering the temporary working platform was a 40% cost reduction, after an allowance for the cost of the geogrids.

Throughout the project, we assisted with the coordination of the proposals, collaborating with the full supply chain, which included Noble Works as the scheme designer and Stantec as the Tier 1 contractor.

E’GRID Biaxial geogrid from Wrekin is a large aperture polypropylene geogrid used to reinforce the ballast layer, reducing ballast settlement and subsequent maintenance intervention following ballast renewal.

E’GRID delivers ground stabilisation under roads, railways (we have a Network Rail certificate of acceptance for E’Grid Biaxial Grid) and paved areas. Employed in single or multilayers, the tough platform created provides tremendous load dispersal, allowing previously weak soils to be reclaimed for a wide range of uses, including, as at Earl Shilton, for access roads and platforms.

When granular particles are compacted over E’GRID Biaxial grids, they partially penetrate and project through the apertures to create a strong and positive interlock. The load dispersal effect from the interlocking mechanism increases shearing resistance within the soil, improving compaction and allowing the sub-base thickness to be decreased, ultimately cutting construction costs and time.

Related case studies

Case study

Providing the answer to access issues at Scottish Wind Farm

We were selected over two other civils manufacturers to provide materials to support the creation of an economical access road to aid the construction of a new wind farm.

Greencat Contracting
Greencat Contracting
Read more
Related case study

£2.5M logistics project propped up with Geoworks geosynthetics

After surveys revealed ground that was too soft to build on, Alto Construct needed to call upon our geosynthetics expertise to recommend the right solution to complete the £2.5 million Newhall Road Distribution Centre.

Alto Construct
Alto Construct
Read more