Home
My Geoworks
Severn Trent Earl Shilton Treatment Works

Earl Shilton Treatment Works

  • Severn Trent

  • Earl Shilton Sewage Treatment Works

  • Biaxial

  • TerraGrid

We were approached by Severn Trent’s contractor to discuss the creation of site access and the installation of a proposed working platform at the sewage treatment works at Earl Shilton, southwest of Leicester.

The works were being developed to increase its waste processing capacity. The proposed plant for the site works required temporary works access as well as a working platform for the concrete pump and hydraulic (Kobelco CKE700) crawler crane.

The traditional approach to working platform design is to use a BR470 design methodology as suggested by BRE – Working Platforms for Tracked Plant (2004). Instead, our technical team proposed a load-spread analysis using TerraGrid Pro Biaxial geogrid. This meant the working platform thickness could be reduced by a further 40% compared to BR470.

Although the application area was not large, the benefit was significant when operating in such confined spaces. Reducing the resources required can have a very positive impact on such a restricted site, not only reducing costs but also minimising the contractor’s construction programme and overheads.

Earl Shilton

The value-engineered solution provided by Geoworks cut our costs by 40%. We were very pleased with the savings made, but also the technical support and the professional levels of service provided.

Sam Harris

MWH Global (Stantec)

Earl Shilton

Within a well-managed time frame, the technical team was able to value-engineer the traditional approach to platform construction. With tight site constraints and limited resources, the impact on value engineering the temporary working platform was a 40% cost reduction, after an allowance for the cost of the geogrids.

Throughout the project, we assisted with coordinating the proposals, collaborating with the full supply chain, which included Noble Works as the scheme designer and Stantec as the Tier 1 contractor.

TerraGrid Pro Biaxial geogrid from Wrekin is a large-aperture polypropylene geogrid used to reinforce the ballast layer, reducing ballast settlement and subsequent maintenance interventions following ballast renewal.

TerraGrid Pro delivers ground stabilisation under roads, railways (we have a Network Rail certificate of acceptance for TerraGrid Pro Biaxial Grid) and paved areas. Employed in single or multilayers, the tough platform created provides tremendous load dispersal, allowing previously weak soils to be reclaimed for a wide range of uses, including, as at Earl Shilton, for access roads and platforms.

When granular particles are compacted over TerraGrid Pro Biaxial grids, they partially penetrate the apertures and project through them to create a strong, positive interlock. The load-dispersal effect from the interlocking mechanism increases shear resistance in the soil, improving compaction and allowing the sub-base thickness to be reduced, ultimately cutting construction costs and time.

Related case studies

Related case study

Hinkley Point C Nuclear Power Station Haul Road

Working with J. Murphy & Sons and Balfour Beatty we helped with the construction of a ten-kilometre haul road to support the first UK nuclear power station to be built in over 20 years. When complete, Hinkley Point C in Somerset will provide low-carbon electricity for around six million homes across the South West.

EDF Energy
Read more
Related case study

£2.5M logistics project propped up with Geoworks geosynthetics

After surveys revealed ground that was too soft to build on, Alto Construct needed to call upon our geosynthetics expertise to recommend the right solution to complete the £2.5 million Newhall Road Distribution Centre.

Alto Construct
Read more