Home
My Geoworks
Hinkley Point C haul road using Geoworks geosynthetics

Hinkley Point C Nuclear Power Station haul road

  • EDF Energy

  • Hinkley, Point C

  • 10 km haul road

  • 100,000 sq m of materials supplied

  • Biaxial

  • E'GRID

J. Murphy & Sons and Balfour Beatty contacted us to help with the construction of a ten-kilometre haul road that would support the first UK nuclear power station to be built in over 20 years. 

When complete, Hinkley Point C in Somerset will provide low-carbon electricity for around six million homes across the South West. However, the existing road network and infrastructure were insufficient to cope with the demands of the construction process.  

We were approached by contractors J. Murphy & Sons and Balfour Beatty to support the creation of a ten-kilometre haul road. This would allow construction traffic to drive directly into the sites where new pylons were being erected and underground cables installed.

We visited the site and discovered it had a high level of variability in soils, but for construction efficiency, a constant cross-section to suit the differing ground conditions was needed.

Hinckley point c power station

We advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross-section in two compaction layers, totalling 550mm.

Shahid Raza

Technical Sales Manager, Geoworks

Hinkley Point C Nuclear Power Station

The significant length of this access road would typically create a substantial drain on the resources required for installation. For this project, we advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross-section in two compaction layers, totalling 550mm.

For the installation, 100,000sq m of our products were used. SX 3030 was installed over a layer of its FasTrack 609 separation geotextile – both with a manufactured four-and-a-half metre width to suit the subgrade interface. 

This substantial reduction in foundation thickness reduced cost and environmental impact while accelerating the construction process.

With the implementation of geogrids, the access road is now operational, enhancing site accessibility for the construction team while allowing onsite HGVs to bypass the local road network.

Through utilising our geogrids instead of traditional foundation methods, the temporary access road can be exhumed at a faster rate and significantly reduced cost once the project is complete.

Overall, this project provides a clear demonstration of value engineering that can be achieved through using geosynthetics.

Related case studies

Related case study

Whittington Rifle Ranges

The existing stop butts at Whittington Ranges had not been used for many years and had fallen into a state of disrepair. Our client was tasked with reinstating the stop butts and bringing them up to current safety standards so that the range could be re-opened for use by the armed forces.

Landmarc
Landmarc
Read more
Related case study

Value Engineered Road for Oak Grange housing development

Our geogrids team value-engineered a fit-for-purpose adoptable road for a new Derby housing development, working with the city council, William Davis Homes and S&L Groundworks. This project demonstrates how value engineering solutions such as geogrids can be used to solve general and site-specific issues for the housing sector.

William Davis Homes
William Davis Homes
Read more