Home
My Geoworks
Hinkley Point C haul road using Geoworks geosynthetics

Hinkley Point C Nuclear Power Station haul road

  • EDF Energy

  • Hinkley, Point C

  • 10 km haul road

  • 100,000 sq m of materials supplied

  • Biaxial

  • E'GRID

J. Murphy & Sons and Balfour Beatty contacted us to help with the construction of a ten-kilometre haul road that would support the first UK nuclear power station to be built in over 20 years. 

When complete, Hinkley Point C in Somerset will provide low-carbon electricity for around six million homes across the South West. However, the existing road network and infrastructure were insufficient to cope with the demands of the construction process.  

We were approached by contractors J. Murphy & Sons and Balfour Beatty to support the creation of a ten-kilometre haul road. This would allow construction traffic to drive directly into the sites where new pylons were being erected and underground cables installed.

We visited the site and discovered it had a high level of variability in soils, but for construction efficiency, a constant cross-section to suit the differing ground conditions was needed.

Hinckley point c power station

We advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross-section in two compaction layers, totalling 550mm.

Shahid Raza

Technical Sales Manager, Geoworks

Hinkley Point C Nuclear Power Station

The significant length of this access road would typically create a substantial drain on the resources required for installation. For this project, we advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross-section in two compaction layers, totalling 550mm.

For the installation, 100,000sq m of our products were used. SX 3030 was installed over a layer of its FasTrack 609 separation geotextile – both with a manufactured four-and-a-half metre width to suit the subgrade interface. 

This substantial reduction in foundation thickness reduced cost and environmental impact while accelerating the construction process.

With the implementation of geogrids, the access road is now operational, enhancing site accessibility for the construction team while allowing onsite HGVs to bypass the local road network.

Through utilising our geogrids instead of traditional foundation methods, the temporary access road can be exhumed at a faster rate and significantly reduced cost once the project is complete.

Overall, this project provides a clear demonstration of value engineering that can be achieved through using geosynthetics.

Related case studies

Related case study

Bristol Airport, Silverzone Car Park

With both an increase in passenger numbers and volume of flights there was a need for the operators of Bristol Airport to undertake a range of improvements across the airport complex to cope with the growing demand. We were able to provide the necessary technical advice and provide a cost-effective alternative in place of the originally specified composite geogrid product.

South West Airports Limited
South West Airports Limited
Read more
Related case study

Warner Brothers Studio

We helped Warner Brothers Studio and earthworks contractor Spadeoak to build new car parking areas as the land where they had previously built car parking on was being reclaimed for new buildings. Our MultiTrack 1000 nonwoven geotextile was laid on the formation to provide separation and filtration.

Warner Brothers Studio
Warner Brothers Studio
Read more